this post was submitted on 06 Sep 2023
1080 points (99.4% liked)

Technology

59312 readers
5006 users here now

This is a most excellent place for technology news and articles.


Our Rules


  1. Follow the lemmy.world rules.
  2. Only tech related content.
  3. Be excellent to each another!
  4. Mod approved content bots can post up to 10 articles per day.
  5. Threads asking for personal tech support may be deleted.
  6. Politics threads may be removed.
  7. No memes allowed as posts, OK to post as comments.
  8. Only approved bots from the list below, to ask if your bot can be added please contact us.
  9. Check for duplicates before posting, duplicates may be removed

Approved Bots


founded 1 year ago
MODERATORS
you are viewing a single comment's thread
view the rest of the comments
[–] [email protected] 4 points 1 year ago (2 children)

this is software speciifcally for assembly line management?

[–] [email protected] 16 points 1 year ago

There is specific software for everything

[–] [email protected] 0 points 1 year ago (1 children)

Yeah a few levels.

Level 1: complex stand alone devices, mostly firmware.

Level 1a. Stuff slightly more complicated than a list of settings, usually for something like a VFD or a stepper motor controllers. Not as common.

Level 2 PLCs, HMIs, and the black magic robotic stuff. Stand alone equipment. Like imagine a machine that can take something, heat it up, and give it to the next machine.

Level 3: DCS and SCADA. Data control center and whatever SCADA stands for, I always forget. This is typically for integrating or at least data collection of multiple stand alone equipment for level 2.

Level 4: the integration layer between Level 3 and whatever means the company has for entering in sales.

Like everything in software this is all general. Some places will mix layers, subtract layers, add them. I would complain about the inconsistent nature of it all but without it I would be unemployed.

[–] [email protected] 1 points 1 year ago (1 children)

Level 1a. Stuff slightly more complicated than a list of settings, usually for something like a VFD or a stepper motor controllers. Not as common.

Level 2 PLCs, HMIs, and the black magic robotic stuff. Stand alone equipment. Like imagine a machine that can take something, heat it up, and give it to the next machine.

Level 3: DCS and SCADA. Data control center and whatever SCADA stands for, I always forget. This is typically for integrating or at least data collection of multiple stand alone equipment for level 2.

Level 4: the integration layer between Level 3 and whatever means the company has for entering in sales.

Like everything in software this is all general. Some places will mix layers, subtract layers, add them. I would complain about the inconsistent nature of it all but without it I would be unemployed

Is this specific software engineering languages? or is this electrical engineering or what kind of work is this?

[–] [email protected] -1 points 1 year ago (1 children)

I am having problems understanding your questions. I generally operate on level 2 and we typically use graphics based languages when we implement scripting languages to do graphical languages. The two most common graphic languages are FBDs and Ladder-Logic. Both have a general form and vendor specific quirks.

For scripting I tend towards Perl or Python, but I have seen other guys use different methods.

Level 3 use pretty much the same tools. Level 4 I have in the passed used a modbus/tcp method but this isn't something I can really say is typical. One guy I know used the python API to do it.

[–] [email protected] 1 points 1 year ago

oh, thank you

my background is not in engineering which explains my confusing questions